Progress and Plans

Welcome to the Mackey Project Progress and Plans page! This page contains photos of the field before work began, photos of project progress so far, and a list of upcoming planned work. We will post regular updates to this page so check back often to see how things are coming along!


Upcoming planned work
  • Week of June 20 - install water and sewer lines

Project progress

The historical progress for the project is summarized lower on this page. These on-page links provide details and photos of each step in our journey to the new Mackey field.


Before the project began

Click here to see a historical view of Mackey Field, before the project began.


Return to Mackey Project overview

Week of Jun 12, 2022

This week, we installed the block walls for the first base dugout.


06/14/2022 - This video shows the footer and foundation block work being installed for the first base dugout and ADA bathroom


06/14/2022 - This video shows the footer and foundation block work being installed for the third base dugout and ADA bathroom


06/15/2022 - This video shows the mostly complete foundation for the first base dugout and ADA bathroom

Return to top

Week of Jun 5, 2022

This week, we installed the construction fencing, surveyed and staked, and poured the dugout footers.

construction fencing and sign
06/09/2021 - Construction fencing and project sign

construction fencing and sign
06/09/2021 - Construction fencing

dugout excavation
06/09/2021 - Dugout excavation

dugout excavation
06/09/2021 - Dugout excavation

first base dugout footer is poured
06/09/2021 - First base dugout footer is poured

third base dugout footer is poured
06/09/2021 - Third base dugout footer is poured

Return to top

2021 Field Prep

Work on the field began by removing the backstop and sideline fencing, the shed behind home plate, and the large tree next to the road. The benches and the pipe railing next to the walking trail were also removed

3rd base bench
03/29/2021 - View of third base bench area from pitcher's mound

1st base bench
03/29/2021 - View of first base bench area from pitcher's mound

Fencing removed
04/24/2021 - View of home plate from pitcher's mound

Behind backstop
04/24/2021 - View of trail and behind backstop, from approximate area of third base bench.

Field view behind backstop
04/24/2021 - View of field from edge of Park Road, behind home plate


Return to top

Before the Project Started

circa 2020 Mackey field

It's good to start any project by documenting how things were before work began, so the improvements in the end product can be fully appreciated. Before the project, Mackey field was a 60-90 field with a dirt infield and a shallow backstop. The benches were uncovered, wooden benches. Wooden bleachers were provided for fans, adjacent to each bench. An open shed was positioned behind the home plate backstop. The Boyertown Park walking path navigated past the field along the third base side, separated from the third base bench by a simple black pipe railing. A large tree was between the walkway and the road. The above photo shows a view of home plate and the backstop from behind the pitcher's mound, taken in 2020.

Return to top

Contact

Boyertown Midget Baseball League
PO Box 34 
Boyertown, Pennsylvania 19512

Email: [email protected]

Copyright © 2022 Boyertown Midget Baseball League  |  Privacy Statement |  Terms Of Use |  License Agreement |  Children's Privacy Policy  Log In