Progress and Plans

Welcome to the Mackey Project Progress and Plans page! This page contains photos of the field before work began, photos of project progress so far, and a list of upcoming planned work. We will post regular updates to this page so check back often to see how things are coming along!


Project progress

The historical progress for the project is summarized lower on this page. These on-page links provide details and photos of each step in our journey to the new Mackey field.


Before the project began

Click here to see a historical view of Mackey Field, before the project began.


Return to Mackey Project overview

Week of Oct 1, 2023

This week, the irrigation and infield sod were installed.

sod and irrigation
10/05/2023 - Install irrigation and sod

Return to top

Week of Aug 20, 2023

This week, work continued on the installation of the infield.


08/21/2023 -Installation of basepaths

base paths
08/24/2023 - Base paths installed

1st baseline
08/24/2023 - View of first baseline

3rd baseline
08/24/2023 - View of third baseline

Return to top

Week of Aug 13, 2023

This week, the home plate and pitchers mound dirt were installed.

Home plate and mound
08/18/2023 - Home plate and pitcher's mound

Pitchers mound view of home
08/18/2023 - Pitcher's mound view of home plate and backstop

3rd base dugout walkup
08/18/2023 - Third base dugout walk-up

1st base dugout walkup
08/18/2023 - First base dugout walk-up

Return to top

Week of Jul 9, 2023

This week, the batting cage poles were installed.

batting cage poles
07/10/2023 - Batting cage poles

Return to top

Week of Jun 4, 2023

This week, infield excavation work was done.

infield excavation
06/07/2023 - Infield excavation

infield excavation
06/07/2023 - Infield excavation

infield excavation
06/09/2023 - Infield excavation

Return to top

Week of May 14, 2023

This week, the field grading was completed and the warning track installed. Construction of the Anthony Rota Memorial was also started.


05/19/2023 -Warning track and field grading

Rota memorial
05/19/2023 - Anthony Rota Memorial

Return to top

Week of Apr 30, 2023

This week, stonework was applied to the concession stand and shed.

steps to press box
05/05/2023 - Concession stand stonework

Return to top

Week of Mar 26, 2023

This week, the steps to the press box were added. We have also included some photos of the completed brickwork and bleacher concrete.

steps to press box
03/31/2023 - Installed steps to press box

field view from press box
03/31/2022 - Field view from press box

commemorative bricks
03/31/2022 - Commemorative bricks on the back of the grandstand

completed bleacher concrete
03/31/2022 - Completed concrete in grandstand area

field view from grandstand
03/31/2022 - Field view from grandstand

Return to top

Week of Feb 26, 2023

This week, concrete was poured in the bleacher area and the final brickwork, including the donated commemorative bricks, was completed.

original Mackey Field plaque
03/03/2023 - Installed original Mackey Field plaque

commemorative bricks
03/03/2022 - Commemorative bricks installed, bleacher concrete poured

Return to top

Week of Feb 12, 2023

This week, concrete was poured in the dugouts and grandstand area.

dugout concrete
02/15/2023 - Completed dugout floor

dugout fencing
02/15/2022 - Outside view of dugout, with completed fencing

grandstand concrete
02/15/2022 - Freshly poured concrete for grandstand footer

Return to top

Week of Nov 13, 2022

This week, we installed the stadium light fixtures.

light install
11/17/2022 - Installing the first base-side lights

light install
11/18/2022 - Installed first base-side lights

Return to top

Week of Oct 2, 2022

This week, we installed the brick on the dugouts and backstop wall.

brick on dugout
10/07/2022 - Brick on dugouts

brick on dugout
10/07/2022 - Brick on dugouts

brick on dugout
10/07/2022 - Brick on backstop

Return to top

Week of Aug 14, 2022

This week, we installed the electrical lines between the dugouts and the back wall of the grandstand.

electrical conduit
08/18/2022 - Electrical lines between dugouts


08/18/2022 - Back wall of grand stand

Return to top

Week of July 24, 2022

This week, we installed the base blockwork for the backstop. Later in the week, the dugout rooves and press box were roughed in.


07/26/2022 - Installation of backstop blockwork

backstop
07/26/2022 - Completed backstop blockwork

backstop
07/28/2022 - Work begins on the roof over the first base dugout and bathroom


07/28/2022 - Completed roof on third base dugout and bathroom

backstop
07/29/2022 - Roughing in the press box

backstop
07/29/2022 - Press box rough work complete!

Return to top

Week of Jun 26, 2022

This week, we completed the blockwork on the first and third base dugouts and ADA bathrooms.


07/05/2022 - This video shows gives a tour of the ADA bathroom and first base dugout

Return to top

Week of Jun 19, 2022

This week, we began block work for the first and third base dugout and ADA bathroom walls.

3rd base dugout
06/23/2022 - Third base dugout and ADA bathroom

3rd base dugout
06/23/2022 - Third base dugout and ADA bathroom

Return to top

Week of Jun 12, 2022

This week, we installed the foundations for the first and third base dugouts and ADA bathrooms.


06/14/2022 - This video shows the footer and foundation block work being installed for the first base dugout and ADA bathroom


06/14/2022 - This video shows the footer and foundation block work being installed for the third base dugout and ADA bathroom


06/15/2022 - This video shows the mostly complete foundation for the first base dugout and ADA bathroom

Return to top

Week of Jun 5, 2022

This week, we installed the construction fencing, surveyed and staked, and poured the dugout footers.

construction fencing and sign
06/09/2022 - Construction fencing and project sign

construction fencing and sign
06/09/2022 - Construction fencing

dugout excavation
06/09/2022 - Dugout excavation

dugout excavation
06/09/2022 - Dugout excavation

first base dugout footer is poured
06/09/2022 - First base dugout footer is poured

third base dugout footer is poured
06/09/2022 - Third base dugout footer is poured

Return to top

2021 Field Prep

Work on the field began by removing the backstop and sideline fencing, the shed behind home plate, and the large tree next to the road. The benches and the pipe railing next to the walking trail were also removed

3rd base bench
03/29/2021 - View of third base bench area from pitcher's mound

1st base bench
03/29/2021 - View of first base bench area from pitcher's mound

Fencing removed
04/24/2021 - View of home plate from pitcher's mound

Behind backstop
04/24/2021 - View of trail and behind backstop, from approximate area of third base bench.

Field view behind backstop
04/24/2021 - View of field from edge of Park Road, behind home plate


Return to top

Before the Project Started

circa 2020 Mackey field

It's good to start any project by documenting how things were before work began, so the improvements in the end product can be fully appreciated. Before the project, Mackey field was a 60-90 field with a dirt infield and a shallow backstop. The benches were uncovered, wooden benches. Wooden bleachers were provided for fans, adjacent to each bench. An open shed was positioned behind the home plate backstop. The Boyertown Park walking path navigated past the field along the third base side, separated from the third base bench by a simple black pipe railing. A large tree was between the walkway and the road. The above photo shows a view of home plate and the backstop from behind the pitcher's mound, taken in 2020.

Return to top

Contact

Boyertown Midget Baseball League
PO Box 34 
Boyertown, Pennsylvania 19512

Email: [email protected]

Copyright © 2024 Boyertown Midget Baseball League  |  Privacy Statement |  Terms Of Use |  License Agreement |  Children's Privacy Policy  Log In